Bloomberg reported on 16 November that HSBC sold a $300 million slice of an $18 billion financing package which funds construction of a campus in Doña Ana County, New Mexico, tied to Oracle at prices in the mid-80s. The sale took place several weeks ago, shortly after Oracle sent a notice to the project's developer citing force majeure.
Should the 2.5GW data centre campus, dubbed Project Jupiter, fail to come online in 2028 as planned, Oracle is seeking to delay the payments it would have to make, rather than forfeit its tenancy. The campus has faced multiple infrastructure setbacks, including delays to a planned natural-gas pipeline and legal challenges over water and air-quality permits.
The syndicated loan totals $18 billion, with approximately 20 banks participating, and is divided into several tranches each linked to different construction projects within the data centre.
Bloomberg said the bank sold its piece in the mid-80s meaning buyers paid about $0.85 per $1 of face value ,a sign they wanted compensation for added uncertainty. If that mid-80s level becomes a benchmark, it could drag down the valuations of other data-centre construction loans and make it harder for banks and private-credit funds to syndicate new tranches without offering better economics.
Oracle sent the force majeure notice to the developer of Project Jupiter, a Stargate data centre campus in New Mexico. Blue Owl Capital, whose unit received the notice, said in a statement to CNBC that "this notice does not change the financial commitments to this multi-year project." Oracle also maintained that it does not expect a delay, saying: "We are fully committed to New Mexico and confident in our path forward."
The move highlights how setbacks at a single project can quickly affect pricing for related debt, and points to a more selective funding environment for developers seeking capital for multibillion-dollar facilities linked to the AI boom.
Source : Bloomberg